The road to opening
Seven stages from derelict pottery shed to first pour.
Stage 3 of 7In progress
01
Completed
Exterior building renovation
New walls, roof, foundation, windows, doors and 3-phase power — finished Winter 2024.
02
Completed
Interior construction
Floor levelling, drain & sump, resin-concrete brewing floor, polymer-resin floor, walls painted, office and storage built.
03
In progress
Equipment selection & purchase
Used 500L Speidel brewhouse (Spain), fermenters & packaging (Czech Republic), CIP cart (Italy) — being finalised and shipped.
04
Upcoming
Water treatment, plumbing & cold room build
RO water treatment, discharge collection, plumbing the brewery kit, and building the walk-in cold room.
05
Upcoming
HSE & Revenue final inspections
Final HSE inspection once equipment is installed, followed by the Revenue Customs & Excise final inspection for the Beer Manufacturer's Licence.
06
Upcoming
Test batches & initial marketing
Full-scale test brews, VAT registration, and initial marketing to our local network.
Grand Opening
3 Flags Brewing opens its doors.